|
Our phone numbers are: day time 570-283-5050 and evenings 570-675-0852
|
|
|
The foundation (1) Many additions are built on pier footings which require; A. Digging 16” diameter holes 42” deep in the ground. Usually 4 to 8 of these. B. Installing forms and steel reinforcing “re-bar” and pouring concrete into them. C. Disposing of the excess dirt. (2) Instead of pier footings, trench footings with concrete or cinder blocks involve; A. Bringing an earth digging machine such as a “Back hoe” or an “Excavator” onto the site, unless you have “youthful” assistance available to manually dig the trench. (Seldom recommended) B. Digging a 16” wide trench 42” deep all around the perimeter of the floor system. C. Form and pour an 8” deep x 16” wide footing with concrete and reinforcing steel bars. D. Laying 8” concrete blocks and covering the outside of them with “parging” ( a thick cement mixture applied to the outside of the exposed blocks.) E. Backfilling the foundation with dirt and then disposing of the remaining dirt. F. In some cases a foundation drain pipe system called a “French drain” will need to be connected to a existing system.. The Flooring (1) The floor can be a wood system or concrete. (3) This would consist of either a number of concrete piers or continuous
foundation wall. (9) Insulation is installed between the floor joists if the sunroom is to be
heated. (11) With a pier system, the area between the floor and the ground can be closed in with a variety of exterior paneling or lattice. (12) Carpet, ceramic tile, or hardwood flooring can be installed for the
finish flooring. |
|
|